Cutover Timeline
Chronological view of the migration weekend (Jan 16 - Jan 20).
Event Schedule
All times in Eastern Standard Time (EST).
Jan 16 • 5:00 PM
VitechData Freeze & Backup
Final database dump and application file backup provided to PointClick.
Jan 17 • 5:00 PM
PointClickData Transfer
Secure download of all assets initiated.
Jan 18 • 5:00 AMCritical Path
PointClickRestoration Begins
Oracle Data Pump import process starts (24h duration).
Jan 19 • 6:00 AM
PointClickRestoration Complete
Database and file system restoration finalized.
Jan 19 • 10:00 AM
NFL PBUAT Validation
Business team begins functional testing.
Jan 19 • 5:00 PMDecision
NFL PBGo/No-Go Decision
Executive sign-off to proceed with cutover.
Jan 20 • 8:00 AMCritical Path
PointClickDNS Cutover
Traffic switched to new AWS environment.
Cutover Window
96 Hours
Total duration from freeze to go-live.
StartJan 16, 5:00 PM
EndJan 20, 5:00 PM
Support Coverage
Hypercare Period
Jan 20 - Jan 22
24/7 Engineering Support