NFL PB Cutover

Cutover Timeline

Chronological view of the migration weekend (Jan 16 - Jan 20).

Event Schedule
All times in Eastern Standard Time (EST).
Jan 16 • 5:00 PM
Vitech

Data Freeze & Backup

Final database dump and application file backup provided to PointClick.

Jan 17 • 5:00 PM
PointClick

Data Transfer

Secure download of all assets initiated.

Jan 18 • 5:00 AMCritical Path
PointClick

Restoration Begins

Oracle Data Pump import process starts (24h duration).

Jan 19 • 6:00 AM
PointClick

Restoration Complete

Database and file system restoration finalized.

Jan 19 • 10:00 AM
NFL PB

UAT Validation

Business team begins functional testing.

Jan 19 • 5:00 PMDecision
NFL PB

Go/No-Go Decision

Executive sign-off to proceed with cutover.

Jan 20 • 8:00 AMCritical Path
PointClick

DNS Cutover

Traffic switched to new AWS environment.

Cutover Window
96 Hours

Total duration from freeze to go-live.

StartJan 16, 5:00 PM
EndJan 20, 5:00 PM
Support Coverage

Hypercare Period

Jan 20 - Jan 22

24/7 Engineering Support